Subcontractor Quality Performance

Quality Score = NCR Close-out (40%) + Inspection RAG (35%) + Audit Items (25%)

71
Avg Quality Score
45
Trades Tracked
18
Good (≥80)
3
Needs Attention
24
Poor (<60)
Quality Score League Table
0255075100Structural SteelErectionMechanicalConcreteRC FrameDrainageAttenuationTank ServicesFoundationsConcreteFrame /MasonrySupportMasonrySupport /ConcreteFrameVentilationDrylining &CeilingsBrickwork &BlockworkCapping BeamWaterproofingDrainage /PlumbingSuperstructureColumns,Walls,Cores,Slabs,BeamsGroundworks,Drainage,WaterproofingConcreteFrameSFS / DryliningOtherCoordinationFlooringScreedingFall ArrestWet RiserResidentialSprinklerCommercialSprinklerBlockworkSmokeVentilationRoofingConcrete Structural SteelRefuse ChuteMechanical &PlumbingCurtain WallingDrainageFire Stopping /MEPPlumbing / MEPBrickwork /MasonryGlazingDrylining / FireProtectionPiling PilingDryliningElectrical
100

Structural Steel Erection

Good

0 contractors · 0 NCRs · 0 inspection activities · 0 audit items

NCR: 100 Insp: 100 Audit: 100
100

Mechanical

Good

1 contractor · 0 NCRs · 0 inspection activities · 0 audit items

NCR: 100 Insp: 100 Audit: 100
100

Concrete

Good

1 contractor · 0 NCRs · 0 inspection activities · 0 audit items

NCR: 100 Insp: 100 Audit: 100
98

RC Frame

Good

0 contractors · 0 NCRs · 0 inspection activities · 11 audit items

NCR: 100 Insp: 100 Audit: 91
98

Drainage Attenuation Tank Services

Good

0 contractors · 0 NCRs · 0 inspection activities · 11 audit items

NCR: 100 Insp: 100 Audit: 91
98

Foundations

Good

0 contractors · 0 NCRs · 0 inspection activities · 11 audit items

NCR: 100 Insp: 100 Audit: 91
94

Concrete Frame / Masonry Support

Good

0 contractors · 1 NCRs · 0 inspection activities · 86 audit items

NCR: 100 Insp: 100 Audit: 74
94

Masonry Support / Concrete Frame

Good

0 contractors · 2 NCRs · 0 inspection activities · 86 audit items

NCR: 100 Insp: 100 Audit: 74
94

Ventilation

Good

0 contractors · 0 NCRs · 0 inspection activities · 86 audit items

NCR: 100 Insp: 100 Audit: 74
94

Drylining & Ceilings

Good

0 contractors · 0 NCRs · 0 inspection activities · 86 audit items

NCR: 100 Insp: 100 Audit: 74
94

Brickwork & Blockwork

Good

0 contractors · 0 NCRs · 0 inspection activities · 86 audit items

NCR: 100 Insp: 100 Audit: 74
92

Capping Beam

Good

0 contractors · 0 NCRs · 0 inspection activities · 39 audit items

NCR: 100 Insp: 100 Audit: 68
91

Waterproofing

Good

0 contractors · 0 NCRs · 0 inspection activities · 49 audit items

NCR: 100 Insp: 100 Audit: 64
90

Drainage / Plumbing

Good

0 contractors · 1 NCRs · 0 inspection activities · 24 audit items

NCR: 100 Insp: 100 Audit: 58
89

Superstructure

Good

0 contractors · 0 NCRs · 0 inspection activities · 11 audit items

NCR: 100 Insp: 100 Audit: 55
89

Columns,Walls,Cores,Slabs,Beams

Good

0 contractors · 0 NCRs · 64 inspection activities · 45 audit items

NCR: 100 Insp: 86 Audit: 74
89

Groundworks,Drainage,Waterproofing

Good

0 contractors · 0 NCRs · 64 inspection activities · 45 audit items

NCR: 100 Insp: 86 Audit: 74
82

Concrete Frame

Good

0 contractors · 11 NCRs · 0 inspection activities · 86 audit items

NCR: 72 Insp: 100 Audit: 74
74

SFS / Drylining

Needs Attention

0 contractors · 2 NCRs · 0 inspection activities · 86 audit items

NCR: 50 Insp: 100 Audit: 74
70

Other

Needs Attention

0 contractors · 4 NCRs · 0 inspection activities · 24 audit items

NCR: 50 Insp: 100 Audit: 58
61

Coordination

Needs Attention

0 contractors · 14 NCRs · 0 inspection activities · 24 audit items

NCR: 29 Insp: 100 Audit: 58
59

Flooring

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Screeding

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Fall Arrest

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Wet Riser

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Residential Sprinkler

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Commercial Sprinkler

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Blockwork

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Smoke Ventilation

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Roofing

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Concrete

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Structural Steel

Poor

1 contractor · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Refuse Chute

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Mechanical & Plumbing

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Curtain Walling

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
59

Drainage

Poor

0 contractors · 0 NCRs · 1 inspection activities · 93 audit items

NCR: 100 Insp: 0 Audit: 75
54

Fire Stopping / MEP

Poor

0 contractors · 1 NCRs · 0 inspection activities · 86 audit items

NCR: 0 Insp: 100 Audit: 74
54

Plumbing / MEP

Poor

0 contractors · 1 NCRs · 0 inspection activities · 86 audit items

NCR: 0 Insp: 100 Audit: 74
53

Brickwork / Masonry

Poor

0 contractors · 3 NCRs · 0 inspection activities · 110 audit items

NCR: 0 Insp: 100 Audit: 71
50

Glazing

Poor

0 contractors · 2 NCRs · 0 inspection activities · 24 audit items

NCR: 0 Insp: 100 Audit: 58
50

Drylining / Fire Protection

Poor

0 contractors · 1 NCRs · 0 inspection activities · 24 audit items

NCR: 0 Insp: 100 Audit: 58
48

Piling

Poor

0 contractors · 1 NCRs · 0 inspection activities · 10 audit items

NCR: 0 Insp: 100 Audit: 50
48

Piling

Poor

0 contractors · 2 NCRs · 65 inspection activities · 187 audit items

NCR: 0 Insp: 85 Audit: 72
25

Drylining

Poor

0 contractors · 32 NCRs · 1 inspection activities · 117 audit items

NCR: 19 Insp: 0 Audit: 71
20

Electrical

Poor

0 contractors · 35 NCRs · 1 inspection activities · 203 audit items

NCR: 6 Insp: 0 Audit: 73